Ultra-short downtime pulley lagging solution

Jiangxi Southern Cement corporation only provides 2 hours of downtime in order to ensure production capacity. DCCD® technicians use partial lagging replacement method, and each time within 2 hours of downtime, cleaning up the partial old glue and do the partial installation of the pulley lagging, and complete the entire pulley lagging replacement task through three shutdowns. It takes advantage of the fact that the slide-lag pulley lagging can be used immediately after installation and no need the curing!